Jun182014
School completed and turned over to Conseil scolaire Centre-Nord
May312014
Sprinkler and security monitoring systems have been completed
Electrified hardware and lockdown systems have been installed
Landscaping is near completion
Apr302014
Toilet and sink installation has been completed
Gymnasium hardwood flooring has been installed
Fire alarm has been installed
Final coat of paint has been completed
Mar312014
Toilet and sink installation has commenced
Gymnasium hardwood flooring is being installed
Installation of interior lights is nearly complete
Science room fume hood has been installed
Jan312014
Installation of ceramic tile flooring is complete
Millwork installation progresses
Installation of wood doors and interior lights have commenced
Dec312013
Mechanical and electrical rough-ins continue
Interior painting continues
Millwork installation has commenced
Nov302013
Drywall installation near completion
Ceramic floor tiling continues
Interior painting progresses
Natural gas meter has been installed
Oct312013
Installation of exterior doors has commenced
Completion of interior masonry walls
Interior painting has commenced
Stairs to student lounge have been installed
Sep302013
Installation of exterior frames and windows has commenced
Roofing is near completion
Installation of site sidewalks continues
Interior masonry is near completion
Aug312013
Exterior drywall installation is complete
Installation of city sidewalks and asphalt is complete
Roofing is ongoing
Jul312013
Structural steel is complete
Metal decking is complete
Exterior steel stud work is ongoing
Jun302013
Erection of structural steel has commenced
Metal decking has commenced
May312013
Foundation installation has been completed
Waterproofing and foundation insulation is underway
Installation of underground utilities has been completed
Apr302013
Installation of foundation pads and piers commenced
Grade beams installation is underway
Installation of underground utilities commenced
Mar312013
Site trailer and fencing have been installed
Site preparation for excavation has commenced
Jan312013
Permanent power transformer has been installed
Feb282014
Drywall installation in the gymnasium is complete
Painting in the gymnasium in complete
Installation of lockers and toilet partitions have commenced
Power plugs have been installed and power has been turned on