Jun192014
School completed and turned over to Chinook's Edge School Division
May312014
Final painting has been completed
Installation of gymnasium hardwood flooring has been completed
Installation of exterior and interior doors have been completed
Phone lines have been installed
Apr302014
Finishing coat of paint progresses
Installation of gymnasium hardwood flooring has commenced
Installation of lockers has been completed
Aluminum entrance has been completed
Mar312014
Finishing coat of paint has commenced
Installation of exterior and interior doors and hardware is ongoing
Installation of interior lights has commenced
Gymnasium basketball nets have been installed
Jan312014
Masonry is near completion
Installation of ceramic tile flooring has commenced
Overhead door has been installed
Dec312013
Installation of exterior doors progresses
Fireproofing continues
Interior painting continues
Millwork installation has commenced
Nov302013
Mechanical and electrical rough-ins are near completion
Gymnasium exterior veneer has been completed
Interior painting progresses
Trees have been planted
Oct312013
Exterior doors have been installed
Floor polishing has commenced
Interior painting has commenced
Installation of sidewalks continues
Sep302013
Roofing is near completion
Installation of drywall has commenced
High performance classrooms have been installed
Hardscaping has commenced
Aug312013
Gymnasium steel has been erected and the metal deck has been installed
Roofing continues
Installation of interior partitions has commenced
Jul312013
Gymnasium joists have been installed
Bus turnaround has been paved
Roofing continues
Installation of windows is ongoing
Jun302013
Roofing has commenced
Construction of exterior walls has commenced
Window framing has commenced
May312013
Erection of structural steel continues
Firewalls masonry has commenced
Construction of parapets is underway
Apr302013
Erection of structural steel continues
Construction wall has been built inside existing library and demolition of exterior wall is underway
Mar312013
Construction of foundations has been completed
Erection of structural steel has commenced
Feb282013
Temporary exit stair tower completed
Jan312013
Permanent power transformer has been installed
Dec312012
Construction has begun
Installation of foundation pad footings, piers and grade beams proceeds
Nov022012
Official sod turning ceremony
Feb282014
Solar tubes have been installed in the music room
Drywall installation in the gymnasium is complete
Science room flooring is complete