Jun172014
School completed and turned over to Conseil scolaire Francosud
May312014
Flag poles, bike racks and garbage receptacles have been installed
Installation of interior and exterior signage has been completed
Hardscaping has been completed
Landscaping has commenced
Apr302014
Installation of acoustic ceiling tiles has been completed
Benches and lockers have been installed in the locker rooms
Counters, sinks and flooring have been installed in the Science Room
Operable acoustic partitions have been installed
Mar312014
Installation of wood doors has been completed
Ceramic tiling has been completed
Hardwood has been installed in the gymnasium and game lines have been painted
Plumbing fixtures have been installed
Jan312014
Installation of lockers is ongoing
Wood and metal doors are being installed
Millwork installations progresses
Dec312013
HVAC rough-in work has been completed
Fireproofing has been completed
Millwork installations have commenced
Interior ceramic tiling has been completed
Nov302013
Concrete topping for music stage room has been completed
Mechanical and electrical rough-ins are ongoing
Masonry veneer has commenced
Interior ceramic tiling has commenced
Oct312013
Aluminum window framing and glazing have been completed
Installation of site concrete has been completed
Interior steel stud framing continues
Sep302013
Roofing has been completed
Aluminum window framing has commenced
Masonry veneer has commenced
Asphalt parking lot and drive lanes have been completed
Aug312013
Roofing commenced
Exterior steel stud framing and masonry work continues
Interior framing has commenced
Grading and preparation for site concrete and curbs has been completed
Jul312013
Erection of structural steel completed
Metal decking completed
Exterior steel stud parapet framing commenced
Jun302013
Foundation construction has been completed
Erection of structural steel has commenced
Interior mechanical underground work has commenced
May312013
Excavation for foundations, roadways and parking lots continues
Mar312013
Site trailer and fencing have been installed
Site has been mobilized
Grading and excavation for foundations has commenced
Mar152013
Students, parents and dignitaries gather for an official ground breaking ceremony
Feb282014
Drywall installation is complete
Gymnasium equipment is being installed
Masonry veneer is complete