Jun302014
School completed and turned over to Rocky View Schools
May312014
Sliding glass doors have been installed
Hardware installation has been completed
Installation of sound panels in the gymnasium has been completed
Landscaping has commenced
Apr302014
Work in mechanical room has been completed
Installation of gymnasium hardwood flooring has commenced
Installation of sound panels in the gymnasium has commenced
Locker installation has been completed
Mar312014
Painting continues
Exterior finishes are near completion
Installation of equipment in mechanical room continues
Jan312014
Drywall installation is near completion on the main floor
Fireproofing is near completion
Installation of the ceiling grid on the second floor is complete
Installation of the elevator is complete
Dec312013
Drywall installation is ongoing
Interior painting has commenced
Millwork installation on the second floor is near completion
Elevator is being installed
Nov302013
Exterior cladding is near completion
Fireproofing is near completion
Mechanical and electrical rough-ins have been completed
Garbage enclosure has been completed
Oct312013
Second floor classrooms are receiving their first coat of paint
Asphalt paving has been completed
Concrete sidewalks are near completion
Millwork has commenced on the second floor
Sep302013
Exterior aluminum window framing is near completion
Primer painting of second floor classrooms has commenced
Installation of concrete sidewalks is near completion
Fireproofing has commenced
Aug312013
Interior steel stud framing on main floor has commenced
Roofing is complete
Interior drywall installation has commenced
Exterior site lighting concrete bases and concrete sidewalk preparation is underway
Jul312013
Asphalt paving commenced
Roofing substantially complete
Aluminum window framing substantially complete
Interior masonry work completed on second floor
Jun302013
Underground mechanical work has been completed
Roofing is ongoing
Exterior window framing has commenced
Interior masonry work for washrooms has commenced
May312013
Parapet framing has been completed
Roofing has commenced
Installation of underground services has commenced
Interior electrical rough-in under the second floor is ongoing
Apr302013
Installation of metal decking commenced
Exterior masonry work continues
Parapet framing commenced
Mar312013
Erection of structural steel continues
Feb282013
Erection of structural steel commenced
Formwork for grade beams and pile caps continues
Jan312013
Concrete placement for grade beams has commenced
Formwork for grade beams and pile caps has commenced
Dec312012
Construction has begun
Site preparation is completed
Nov162012
Official sod turning ceremony
May312013
Parapet framing has been completed
Roofing has commenced
Installation of underground services has commenced
Interior electrical rough-in under the second floor is ongoing
Feb282014
Radiant panel installation on second floor is complete
Drywall installation on main floor is near completion
Lockers have been installed