Jun302014
School completed and turned over to Grasslands Public Schools
May312014
Millwork is near completion
Flooring and painting is near completion
Installation of lockers, partitions and sound baffles is new completion
Hardscaping has commenced
Apr302014
Installation of millwork has commenced
Flooring and tiling is near completion
Installation of gymnasium equipment progresses
Installation of doors, hardware and lockers is near completion
Mar312014
Painting continues
Exterior finishes are near completion
Installation of equipment in mechanical room continues
Jan312014
Drywall installation continues
Interior painting has commenced
Rough-in of fire sprinkler is near completion
Dec312013
Plumbing, HVAC and electrical rough-ins continue
Drywall installation has commenced
Installation of window frames and exterior glazing have been completed
Nov302013
Plumbing, HVAC and electrical rough-ins have commenced
Roofing is near completion
Interior framing and masonry block commences
Oct312013
Installation of windows has commenced
Parking lot and bus lane have been paved
Exterior site grading continues
Exterior masonry has commenced
Sep302013
High performance classrooms have been installed
Exterior masonry block and veneer continues
Roofing has commenced
Rough-in of underground plumbing has been completed
Aug312013
Structural steel is substantially complete
Exterior masonry block and veneer has commenced
Rough-in of interior underground plumbing has commenced
Jul312013
Completion of foundation pads and piers
Installation of weeping tile completed
Backfill continues
Installation of deep utilities (storm, sanitary and water) completed
Jun302013
Construction of foundation pads and piers continues
Installation of weeping tile to the east side of the building has commenced
Backfill has commenced
May312013
Construction of foundations continues
May302013
Students, parents and dignitaries gathered for an official sod turning ceremony
Mar312013
Site trailer and fencing have been installed
Site has been mobilized
Grading and excavation for foundations has commenced
Dec312012
Site preparation has begun
Feb282014
Fire spray and gas service have been installed
Drywall installation progresses
Plumbing, HVAC, and electrical rough-ins progress