Jun202014
School completed and turned over to STAR Catholic Schools
May312014
Final cleaning and paint touch-ups
Landscaping and site concrete has been completed
Insulation of the mechanical room has been completed
Apr302014
Fencing has been completed
Seasonal work has commenced with pouring of sidewalks
Installation of gymnasium flooring has been completed
Final painting is in the process
Mar312014
Installation of site lighting has commenced
Site clean-up is ongoing to prepare for sod installation
Tiling has been completed
Hardwood flooring is near completion
Jan312014
Elevator installation is complete
Fireproofing is complete
Electrical room has been energized
Lockers have been installed on the second floor
Dec312013
Gymnasium equipment has been installed
Fireproofing is near completion
Installation of decorative column has been completed
Wood doors and hardware have been installed
Nov302013
Gymnasium has been painted and equipment is on site
Interior masonry has been completed
Mechanical work piping, ducting and equipment are near completion
Elevator installation has commenced
Oct312013
Installation of gymnasium drywall has commenced
Landscaping continues
Tiling on second floor has been completed
Interior painting is ongoing
Sep302013
Gymnasium masonry has been completed
Site paving has been completed
Landscaping has commenced
Site lighting and fencing have been installed
Aug312013
Gymnasium masonry has commenced
Second floor drywalling is complete and taping has commenced
Roofing has been completed
Installation of site concrete is ongoing
Jul312013
Installation of parapets and exterior walls is ongoing
Parking lot has been cut and shaped
Roofing is ongoing
Construction of interior and exterior steel studs and drywall continues
Jun302013
Gymnasium masonry has commenced
Exterior masonry and cladding are ongoing
May312013
Roofing construction is ongoing
Firewalls have been installed
Parking lot has been cut and shaped
Apr302013
Erection of structural steel continues
Roofing commenced
Masonry commenced
Mar312013
Erection of structural steel continues
Gas line has been installed
Feb282013
Grade beam construction completed
Erection of structural steel commenced
Elevator shafts constructed
Jan312013
Installation of rebar has commenced
Interior deep water line and sanitary line have been installed
Foundation construction has been completed
Dec312012
Foundation construction continues
Installation of grade beams and pile caps has been completed
Nov022012
Official sod turning to celebrate new joint school
Nov052013
Installation of gymnasium drywall has commenced
Landscaping continues
Tiling on second floor has been completed
Interior painting is ongoing
Feb282014
Wood doors have been installed on main floor
Drywall installation is near completion
Flooring has been installed in the Science Room