Jun302014
School completed and turned over to Rocky View Schools
May312014
Sliding glass doors have been installed
Landscaping has commenced
Hardware installation has been completed
Apr302014
Finishing coat of paint on second floor has been completed
Installation of gymnasium equipment has been completed
Gymnasium hardwood flooring has been installed
Tracks for sliding doors have been installed
Mar312014
Ceiling tiling on second floor is complete
Finishing coat of paint on second floor has commenced
Installation of gymnasium equipment is near completion
Jan312014
Ceramic tiling in washrooms is complete
Installation of gymnasium masonry wall and veneer are complete
Lockers have been installed on the second floor
Dec312013
Ceramic tiling in washrooms progresses
Elevator has been installed
Interior painting of classrooms has commenced
Fire proofing has been completed
Nov302013
Mechanical and electrical rough-ins are near completion
Elevator and lockers have been delivered
Interior masonry has been completed on the main floor
Fire proofing is ongoing
Oct312013
Ceramic tiling in washrooms is near completion
Drywall installation has commenced
Interior masonry has commenced
Sep302013
Interior drywall installation has commenced
Fire proofing has commenced
Exterior masonry continues
Aug312013
Interior masonry block for the second floor has been completed
Modular classrooms have been delivered to the site
Exterior cladding has commenced
Jul312013
Roofing is substantially complete
Exterior stud framing for the walls and parapets is substantially complete
Concrete curbs and gutters completed for the parking lot, walks and bus stop
Asphalt paving completed in parking lot
Jun302013
Roofing has commenced
Exterior frames for the windows are being constructed
Metal cladding on the north and south elevations has commenced
Interior masonry is ongoing
May312013
Structural steel installation has been completed
Metal decking has been constructed
Structural steel stairs for the interior have been installed
Underground services within the building footprint have been installed
Apr302013
Deep services for the waterline have been installed
Fire hydrant has been installed
Installation of metal decking and roof parapets commenced
Mar312013
Erection of structural steel continues
Feb282013
Grade beam installation completed
Erection of structural steel for Division I completed
Erection of structural steel for Division II commenced
Jan312013
Pile installation has been completed
Grade beam installation has commenced
Dec312012
Construction has begun
Installation of foundation pad footings, piers and grade beams proceeds
Nov162012
Students, parents and dignitaries gather for an official ground breaking ceremony
Feb282014
Ceramic tiling in washrooms is complete
Drywall installation on main floor progresses
Gymnasium is near completion and ready for athletic equipment